Guide · Energy savings performance contracts How energy savings performance contracts work for government facilities

A plain guide for contracting officers and facility managers. It covers how an ESPC gets paid for, who guarantees the savings, the five federal phases, and how Kentucky's state and local programs work.

Matthew Melton, Director of Engineering

An energy savings performance contract (ESPC) lets a government agency upgrade a building without waiting for capital funding. An energy service company (ESCO) develops and installs the improvements, guarantees how much they will save, and is paid over time out of those savings. On a federal contract that period can run as long as 25 years, and if the savings come up short, the agency does not pay for the shortfall.

This guide walks through what federal law requires, the five phases of a federal ESPC, how the savings get proven each year, and how Kentucky’s state and local programs differ. It is written for contracting officers, facility managers, and anyone weighing an ESPC for a public building. Every rule here links to its source at the end.

The short version

  • No up-front capital is required. Payments come out of money the agency already spends on energy and related operations and maintenance. Federal agencies may also put appropriated funds, private financing, or any mix of the two toward a project.
  • The savings are guaranteed. Federal law requires the contract to guarantee savings to the agency. If measured savings fall short, the agency withholds the shortfall from later payments and the ESCO has to correct the problem.
  • Contracts can run up to 25 years. That is the federal ceiling, and agencies may not adopt policies that cap it lower.
  • The savings are proven every year. The ESCO measures and verifies the savings and reports them annually, and the agency reviews that report before reconciling payments.

What federal law requires

Federal ESPCs are authorized by 42 U.S.C. § 8287. The rules that shape every project:

  • A guarantee of savings. The contract must guarantee savings to the agency and set a payment schedule that reflects that guarantee.
  • A ceiling on total cost. What the agency pays each year to its utilities and to the ESCO combined may not exceed what it would have paid for utilities without the contract.
  • Payments from energy budgets. Under DOE’s regulations, payments may come only from funds available for energy expenses and related operations and maintenance.
  • Flexible funding. Agencies may use appropriated funds, private financing, or any combination. Since 2020, energy and water incentives, rebates, grid-services revenue, and credits can also go toward the project.
  • A 25-year maximum term. Agencies may not set internal policies that limit contracts to a shorter term.
  • An annual energy audit. The statute requires it, and it is the basis for the yearly measurement and verification report described below.

The five phases of a federal ESPC

The Federal Energy Management Program (FEMP), part of the Department of Energy, organizes a federal ESPC into five phases. On DOE’s own contract vehicle, they run like this.

Phase 1: Acquisition planning

The agency assembles its acquisition team, writes an acquisition plan, and brings on a project facilitator, an ESPC specialist who guides it through the process. It also decides how it will choose an ESCO: on qualifications alone (Selection Based on Qualifications), or after reviewing preliminary assessments (Selection Based on Preliminary Assessment).

Phase 2: ESCO selection and preliminary assessment

The agency posts a Notice of Opportunity on SAM.gov to every ESCO that holds DOE’s contract and evaluates the responses. The selected ESCO delivers a preliminary assessment, a first look at which energy conservation measures make sense and roughly what they would save. The agency then makes a go/no-go decision and issues a notice of intent to award.

For specific measures or smaller projects, FEMP’s EPC Direct pathway lets an agency skip the preliminary assessment report, or replace it with a presentation, and go straight to the investment-grade audit.

Phase 3: Project development

The ESCO performs an investment-grade audit: a detailed engineering study that sets the energy baseline, the measures, their cost, and the savings it will guarantee. It then submits a task order proposal. The agency witnesses the baseline measurements, negotiates, completes any required notice to Congress, and, on DOE’s contract, gets authorization from DOE’s contracting officer before awarding.

Phase 4: Project implementation and construction

The ESCO designs, installs, and commissions the measures, then performs post-installation measurement and verification. The agency reviews the work, inspects it, and accepts the project. This is the phase where the trades do most of the work: lighting, controls, electrical distribution, HVAC, and the construction that ties them together.

Phase 5: Post-acceptance performance

For the rest of the contract term, the ESCO provides any operations and maintenance it agreed to, measures and verifies the savings, and submits an annual report. The agency witnesses the measurement and verification, approves the report, reconciles the savings at least once a year, and makes payments.

Contract vehicles

  • DOE’s ESPC IDIQ, Generation 4. DOE awarded the current contract on August 3, 2023, to 20 ESCOs, each with a $5 billion ceiling. Agencies can place orders through August 2, 2028, with an option period to August 2, 2033, and task orders can run up to 25 years.
  • Agency vehicles. Some agencies run their own. DOE lists the U.S. Army Corps of Engineers’ ESPC contract and the VA’s ESPC contract alongside its own, and all three are open only to ESCOs on DOE’s Qualified List.
  • ESPC ENABLE is retired. The General Services Administration retired ENABLE, the streamlined program for smaller federal projects, in March 2025. No new ENABLE projects can start, though awarded projects continue through their performance periods. FEMP now points smaller projects to EPC Direct.
  • A UESC is something different. A utility energy service contract is a limited-source acquisition with the agency’s serving utility, under a separate law (42 U.S.C. § 8256). An ESPC is competed among qualified ESCOs and carries the statutory savings guarantee.

The DOE Qualified List of ESCOs

DOE maintains a list of energy service companies qualified for federal ESPC work, under the Energy Policy Act of 1992 and 10 C.F.R. § 436.32. DOE updates it at least once a year, firms recertify annually, and it holds about 90 companies.

Being on the list is the price of entry. It is required to compete for DOE’s contract, the Army Corps’ contract, and the VA’s. An agency running its own ESPC outside those vehicles must use DOE’s list unless it builds its own under the same procedures. In DOE’s own words, though, the list “does not provide direct business opportunities.” It is a qualification, not a contract.

How the savings are proven

Federal ESPCs follow FEMP’s M&V Guidelines: Measurement and Verification for Performance-Based Contracts, now at Version 5.0 (September 2024). Each measure is verified with one of four options:

OptionWhat gets measuredCommon fit
A: Retrofit isolation, key parameterThe key factor is measured; others, such as operating hours, are stipulatedLighting retrofits
B: Retrofit isolation, all parametersEverything that drives the measure’s savings, measured at the system levelMotors, drives, and pumps
C: Whole facilityUtility or whole-building meter data, usually analyzed by regressionProjects with many interacting measures
D: Calibrated simulationA computer model of the building, calibrated to billing or interval dataMeasures that are hard to meter directly

The ESCO submits an annual report within 30 days after each anniversary of project acceptance, and the agency reconciles the savings against the guarantee at least once a year. On our University of Kentucky student-housing lighting project, we performed post-installation measurement and verification under the FEMP guidelines in force at the time (Version 4.0). Our measurement and verification page covers how we set baselines and report.

Kentucky’s state and local programs

Kentucky has its own performance-contracting laws, and they differ from the federal rules in a few important ways.

State agencies and universities

State buildings fall under KRS 56.770 through 56.784, and the Finance and Administration Cabinet’s Division of Facility Efficiency manages the state’s Guaranteed Energy Savings Performance Contracting program.

  • Procurement is by request for proposals and competitive negotiation, and the top-ranked offeror performs the audit.
  • Payments come from measured and verified savings, and the contractor is liable if the savings fall short.
  • The term has no fixed number of years. A contract may not run longer than the life of the energy savings it generates.
  • Oversight: universities that manage their own capital construction follow the Cabinet’s ESPC regulation. State agencies need approval from the Office of Financial Management, and contracts are reported to the Capital Projects and Bond Oversight Committee.

Part of this law was amended in 2026, effective July 15, 2026, so confirm current requirements with the Division of Facility Efficiency before starting.

Cities, counties, and school districts

Local public agencies, including cities, counties, and school districts, fall under KRS 45A.345 through 45A.353. They procure by request for proposals, require a written savings guarantee, and reconcile savings every year. If savings fall short, the provider pays the difference within 30 days. School projects also need approval from Kentucky’s Commissioner of Education. There is no statewide prequalified list; each local agency decides which providers are qualified.

Where A Total Solution fits

A Total Solution is a service-disabled veteran-owned small business based in Louisville. Both A Total Solution, LLC and our joint venture with CMTA, ATS-CMTA JV, LLC, are on DOE’s Qualified List of ESCOs as of November 2026. CMTA, our mentor in the joint venture, holds a DOE Generation 4 ESPC contract and brings more than 50 million square feet of performance-contracting experience.

What we add is the installation side. Most energy conservation measures come down to lighting, controls, electrical distribution, and the construction around them, and our own crews self-perform that work, so the trades answer to one schedule and one safety plan. If you are an ESCO looking for an SDVOSB installation partner, our lighting retrofit brand’s guide to SDVOSB subcontracting goals on ESPCs covers how that work counts toward your plan.

Common questions

Does an ESPC require capital funding?

No. A federal ESPC can be paid entirely from the savings, though agencies may add appropriated funds, private financing, or incentives to the mix.

How long can an ESPC run?

Up to 25 years on a federal contract. In Kentucky, a state contract may not outlast the life of the savings it generates, and a local contract runs for the term the agency sets.

What happens if the savings fall short?

On a federal ESPC, the agency withholds the shortfall from future payments and the ESCO must correct the problem. Under Kentucky law, the contractor is liable for a shortfall on state contracts and must pay it within 30 days on local ones.

Sources

  1. 42 U.S.C. § 8287, Authority to enter into contracts (Cornell Legal Information Institute)
  2. 10 C.F.R. Part 436, Subpart B, Methods and procedures for energy savings performance contracting (eCFR)
  3. DOE ESPC IDIQ Generation 4 Ordering Guide, Revision 1 (August 2024) (DOE)
  4. DOE ESPC Generation 4 IDIQ energy service companies (FEMP)
  5. Process for procuring a federal energy savings performance contract (FEMP)
  6. Energy savings performance contract ENABLE for federal projects (FEMP)
  7. DOE Qualified List of energy service companies (FEMP) and the November 2026 list
  8. M&V Guidelines: Measurement and Verification for Performance-Based Contracts, Version 5.0 (FEMP, September 2024)
  9. About utility energy service contracts (FEMP)
  10. KRS 56.770 and KRS 56.784, state energy savings performance contracts (Kentucky General Assembly)
  11. 200 KAR 5:350, Energy savings performance contracts (Kentucky Administrative Regulations)
  12. KRS 45A.345 and KRS 45A.352, local public agency contracts (Kentucky General Assembly)